Augusta Savage Art & Community Center Cafetorium

Description 

A complete renovation of the interior of the former Dunbar High School Cafetorium, including rebuilding kitchen as a commercial kitchen and auditorium stage, new auditorium flooring, and new plumbing, electrical wiring, and HVAC systems. 

Budget

Total $1,397,600 in Community Development Block Grant CARES Act funding

Current Progress

Selecting architect for design plan as of March 2023; City Council to approve contractor for design by end of April 2023

Timeline

Once design plan is approved and contractor for construction selected, estimated to take 24 months to complete