Description
Construction of an eight-foot wide paved sidewalk trail along Martin Luther King Jr. Blvd. between Vera Francis Hall Park and Palmetto Ave., along Oak Street to US 17, and along N Orange Avenue from Governors Creek Bridge to Harbor Road. Once complete, it will continue the existing trail from Harbor Road through city limits to the south end of the city.
Budget
Total cost $1,545,000 through Florida Department of Transportation funding. Managed by City as a Local Area Project through FDOT.
Current Progress
Construction began September 2022 and is anticipated to be complete by July 2023.