Supervisory Control & Data Acquisition (SCADA) Installation

SCADA Progress: 30%

Description: SCADA installation will streamline the troubleshooting process for the Electric Department and decrease the duration of power outages city-wide.

Budget: $500,000

Current Progress: City finalized design as of October 2020. City will install fiber by April 1, 2021, and contractor will complete remainder of work. Construction is anticipated to be complete by July 2021. City is now working on fine-tuning the system. 

Timeline: Installation complete August/September 2022.